- Constructed a 1580 meter long rubble stone sea erosion protection wall to safeguard local village infrastructure.
- Laid 78,407 sqm of high-durability geo-fabric filter layer and stone-grit-filled jute/nylon bags.
- Sourced, transported, and laid 247,951 m³ of heavy-graded armor rock stones, with individual stones weighing up to 3.5 MT, during intense tidal restrictions.
- Executed large-scale coastal protection works under challenging tidal and marine conditions, ensuring uninterrupted progress and site safety.
- Managed precise placement and grading of heavy armour rock to achieve the required erosion protection profile and structural stability.
- Coordinated material logistics, manpower, and equipment for efficient handling and installation of high-volume coastal protection materials.