Construction of Left Out Works including Junagadh Bypass

Construction of Left Out Works including Junagadh Bypass (Length 19.80 KM) on four-laning of Jetpur Somnath Section of NH 151 (old NH 8 D) between KM. 0.000 to 123.454 in the state of Gujarat.

Project status

Completed

Location

Junagadh, Gujarat

Project Overview

Contract Period

-

Location

Junagadh, Gujarat

Progress

100%

Completion Date

April 1, 2021

Project Value

₹ 198.55 Cr

Construction of Left Out Works including Junagadh Bypass

Client: Under The ES Company for Gawar Construction Ltd. Hisar

 

  • Construction of balance/left-out works including the Junagadh Bypass for the four-laning of the Jetpur–Somnath Section.
  • Executed construction works along the 19.80 Km Junagadh Bypass to improve regional connectivity and traffic movement.
  • Developed four-lane highway infrastructure to enhance road capacity, safety, and operational efficiency.
  • Carried out major roadway, pavement, drainage, and associated civil infrastructure works in accordance with project specifications.
  • Managed construction activities, material resources, equipment, manpower, and site coordination to maintain project quality and schedule.
  • Implemented durable highway infrastructure solutions to support improved connectivity between Jetpur, Junagadh, and Somnath.

Completed despite severe RoW (Right of Way) constraints, maintaining high quality standards and achieving completion within the stipulated schedule.

View related Works