- Rehabilitated and strengthened structural armor across deep-water sections exposed to severe wave overtopping.
- Placed 4,45,727 MT of graded core and primary armor rock stones to enhance coastal protection and structural stability.
- Cast and positioned 1,01,593 m³ of high-performance M-30 grade concrete tetrapods, ranging from 2T to 24T units.
- Executed heavy marine construction activities under challenging wave, tidal, and deep-water working conditions.
- Ensured accurate placement and interlocking of large armor units to improve wave energy dissipation and prevent erosion.
- Coordinated large-scale material handling, concrete production, transportation, and placement operations to maintain project schedules.